Banks High School Modernization
The major component of work on the Bond is the Banks High School Modernization Project.
This work includes major demolition of existing spaces, and rebuild of a new building addition.
BHS Modernization Project
ESTIMATED DATES | PROJECT FOCUS |
Early Spring 2025 | Complete Schematic Design |
Early Fall 2025 | Complete Design Development |
Winter 2026 | Completion of Construction Documents |
Winter 2026 | Begin Early Site Grading Work |
Winter/Early Spring 2026 | Complete Subcontractor Bidding |
Winter 2026 – Fall 2027 | Construction of BHS Addition |
Summer 2027 | Complete North Wing Demolition & Parking Lot Upgrades |
Fall 2027 | Opening of New High School Addition |
Below are some of the key spaces that will be included in the new Banks HS addition:
2D & 3D Art |
Counseling |
General Classrooms |
High School Administration |
Library |
Life Skills |
Marketing & Graphics |
Science Classrooms |
Conceptual Designs of
BHS Modernized Buildings
.